Cogeneration plant in Foret – la Zaida

FMC-FORET, S.A.

The steam demand in the factory (average of 24 t/h with peaks up to 35 t/h at low pressure) made FOREL decide to install a simple cycle plant, with a 12.5 MW gas turbine, that allowed the production of 35 t/h of saturated steam at 10 bar in a heat recovery steam generator (HRSG).

The main equipment was located outdoors (as usual in chemical industries) and buildings to locate control panels, electrical equipment and gas systems were constructed.

After that, in order to maximize the exhaust gases utilization, a steam turbine was installed, which allowed to keep the plant at full load and with high efficiency all the time

AESA’s contribution to the project consisted of the redefinition of the Basic Engineering and the development, purchasing and permits management, construction management, supervision of the installation commissioning and performances tests.

Client: FMC-FORET, S.A.

Tecnology: Combined cycle gas turbine

Power Range: from 10 to 25 MW

Fuel: Natural Gas

Country: Spain

City: La Zaida (Zaragoza)

Related projects

Cogeneration plant in Ajover

5MW cogeneration plant for the supply of steam, electricity and thermal oil to the chemical industry that AJOVER has in Cartagena de Indias (Colombia).

NOTE! This site uses cookies and similar technologies.

If you not change browser settings, you agree to it. Learn more

I understand