Cogeneration plant in Nestlé Girona

NESTLÉ ESPAÑA S.A.

Nestlé España had in its factory in Girona a cogeneration plant, installed by AESA, with two cogeneration lines in simple cycle with gas turbines, installed in 1990 and 1997 with 3.8 and 4.8 MW respectively, able to produce 25 t/h of steam in each line with two heat recovery steam generator (HRSG) (one per line).

In 2010, Nestlé decided to refurbish the first cogeneration line, increasing its electric power and global efficiency with a new 5.2 MW gas turbine.

AESA carried out the engineering, project management; permit management, assistance in purchasing management, construction management and commissioning assistance.

Client: NESTLÉ ESPAÑA S.A.

Tecnology: Simple cycle gas turbine

Power Range: from 5 to 10 MW

Fuel: Natural Gas

Country: Spain

City: Girona

Related projects

Cogeneration plant in KAO Corporation

Substantial refurbishment of the existing cogeneration plant of KAO Corporation replacing its gas turbine for other with grater electrical output.

Cogeneration plant in BASF - Tarragona

Simple cycle cogeneration plant with a 7MW gas turbine and a HRSG with afterburner which was designed to operate as an emergency plant and some years later was extended to 13 MW.